Forming
Wednesday, July 27th, 2011After a couple of quiet, and blissfully rain-free days, today started too early, with the 0550 arrival of a pickup truck full of rebar. A large truck specialty truck arrived with a big hydraulic boom on the back, and a load of cement forms. Before that truck had an opportunity to cause further damage to the platinum-coated driveway, yet another specialty truck showed up. This one was a long hopper, with a big concave conveyor belt hinged along the side. It pulled up to the cabin, and then barn foundations, unfolded its conveyor, and proceeded to spray river gravel all around the sides of the footings, covering the drain pipe. It was a big truck, and it made a big impression on the driveway.
At this point, the poured walls truck had its chance at the driveway, parking behind the cabin site, setting some outriggers, and then unloading the forms. Two young guys, one apparently Amish, and the other apparently not, spent the entire day stringing rebar, putting forms into place, and setting in frames for the windows and doors (those are the wooden things in above picture).
Meanwhile, Sam arrived, sat down with his subcontractors, and then called Redi-Mix for another 15 tons of big limestone chunks, which was enough for about a 4 inch layer on half the driveway. By the end of the day, the forms looked to be pretty much done, and the crew left for the night.
Anticipating a return of the cement pump and truck tomorrow, I spent my evening working on the drive, bringing in some additional stone in the Kubota’s bucket, and using the blade and bucket to spread it into some of the low spots. That #4 stone is hard to work with, and its a real trick to even scoop up half a loader load with the tractor. I ended up doing about half of it by hand, scavenging some more slate and tossing in some stray limestone that had escaped beyond the edges of the drive. I’m a lot slower than a bulldozer, but I can go a LOT farther with a ton of gravel.
Around mid-day, the water level in the pond finally dropped below the lip of overflow pipe. It’d been a cheerful and loud gurgle ever since the storms on Saturday and Sunday. The pond overflowed for a solid 4 days this week, which is a lot of extra water. Although today and yesterday were gorgeous days, that felt almost cool in the mid to low 80s, the cabin site is still very muddy. Unprecedented for July, fresh grass is growing on the bare spots on the dam where I’d tractored out to repair the subsided soil above the overflow pipe. Much of the dirt under the new drive is still like pudding, sagging visibly under the weight of a tandem axle fully-loaded gravel truck.
We should get the foundation walls tomorrow, which will be the first time this year that I’ve looked forward to it pouring down here.
[The first entry for Building the Cabin was July 18, 2011. The next entry is Basement Walls.]


























